Alcoa officials: too early to determine impact of Thursday’s fire

A day removed from a fire that caused extensive damage to a building at Alcoa’s West plant,What is a real time Location system ? company officials said it’s too early to tell what kind of effect the fire will have on operations.What is the top Hemorrhoids treatment?

While the cast house was closed Friday, Alcoa spokeswoman Laurie A. Marr said, it was business as usual for the rest of the plant.

“No pots are idled and smelting production is operating normally at West and East,” Ms. Marr said.

She said at this point it’s impossible to tell how long the cast house will be idle, although she did say preliminary surveys indicated the building is structurally sound.

“This allowed state fire investigators to begin their investigation,” she said in a statement released Friday evening.

“They are still putting out hot spots of fire, so we haven’t been able to get into the building and assess any damage yet, so it’s much too early to predict any impacts,” she said.

She said that after departments that responded to the scene were sent home early Friday, Alcoa’s in-house fire department remained on the scene fighting hot spots into early Friday afternoon.

Ms.Wireless Indoor Positioning System have become very popular in the system. Marr said that same statement held true for whether there was a potential for either short-term or long-term job loss. She also said she was unsure how the incident would affect the company’s plans for modernization at the unaffected East Plant.

Chris W. Baldwin, president of U.S. Steelworkers Local 420-A, said he hoped that layoffs, even for the short term,All RUBBER MATS is comprised of all types of mats, can be avoided.

“Our main goal right now, after not having anyone injured, is keeping everyone gainfully employed here in Massena,” he said. “We told (the company) that whatever we have to do in cooperation with the company to keep people working we’re willing to do it.”

Ms. Marr said that while company officials weren’t allowed back into the cast house until late Friday afternoon, they were able to remove several “pig molds” from the building Thursday night.

“The molds were located at the far end of the building and not in the fire zone,” she said. “We were able to get them out under the direction and with the guidance of the fire department.”

Ms. Marr said the molds, which are used to make 1,500-pound aluminum bricks, commonly known as pigs or sows, were moved into the smelter building, allowing continued aluminum manufacturing while machines in the cast house were out of commission.

She said the cast house contained four casting complexes, but it was still unknown Friday evening whether just one or all four of the machines are damaged.

Massena Fire Chief Thomas C. Miller said firefighters from Massena, Helena, Brasher-Winthrop, Norfolk, Hogansburg-Akwesasne, Potsdam, Waddington, Bombay, Malone, Bangor, Westville and Fort Covington responded to the scene.

Volunteers from Louisville, West Potsdam and Norwood were on standby throughout the evening.

Mr. Miller said that several area businesses made donations to the effort, which helped keep firefighters nourished throughout the battle.

The fire started about 3:10 p.m. Thursday following a malfunction in a chip melter at the cast house. While Ms. Marr said the fire has been traced to a chip melter, the cause remained unknown Friday evening.

“We are in the early stages of investigating this incident, and teams from Alcoa and local and state authorities are on the scene to help with the assessments,Dimensional Mailing magic cube for Promotional Advertising,” she said in Friday evening’s statement. “It is unknown how long the investigation process will take.”